SQA Higher Applications of Mathematics Planning and Decision Making overview quiz quiz
15questions. Pick an answer and you'll see why right away.
The minimum completion time of a project equals the length of which path through the network?
What is the float of an activity on the critical path?
Float is calculated as
A project's two routes take and days. The minimum completion time is
Activity A occupies days to and B must follow A. On a Gantt chart B starts at the earliest on
On a Gantt chart, two activities running in parallel appear as
If two activities that could run in parallel must share a single team, the schedule
What does PERT primarily focus on?
The expected value of an option is calculated as
An option gives with probability and with probability . Its expected value is
To choose between profit options on an expected-value basis, you pick the one with the
On a decision tree, you reach the best choice by
Two options have the same expected value but different spreads of outcomes. Expected value alone ignores
An activity has earliest start day and latest start day . The activity is
To shorten a project's overall duration you must shorten an activity that is